The Hot Commissioning of first tunnel at Bhandewadi, Nagpur plant, on 28th April 2026.

First Tunnel Hot Commissioning – On Tuesday, 28 April 2026, a key milestone was achieved with the process (Hot) commissioning of plant’s first tunnel.

The process formally began at 12:30 PM with a ceremony led by our Group CEO Mr. Kedar Vaze.

Following the ceremony, the tunnel operations were initiated, and the controlled filling of organic fraction of Municipal Solid waste and the dry fermentation process successfully started.

Dry Anaerobic Digestion Process to generate Biogas has as cycle of around 23 days and the Biogas supply will be available by 20th May 2026.

This marks an important step forward in our waste-to- CBG (energy) operations and reinforces our commitment to sustainable waste management.

Hon. Municipal Commissioner of Nagpur Municipal Commissioner, along with his team, visited the site to oversee the process and review the progress.